BEST CENTER
Cleaning and adjustment of the land / site location, execution of deep foundation in piles and concrete blocks and foundations. Cleaning and adjustment of the site / location of the work, execution of the deep foundation in propeller piles and concrete blocks and foundations, raising of the structure in cast-in-place and pre-molded reinforced concrete, roofing in metallic structure, ceramic block masonry closings, and internal drywall partitions, rough/thin coating, painting, and finishes, floor and wall coverings, metallic window and door frames, landscaping and external paving, medium voltage power entrance 13.8 Kv and 225 kvA transformer, medium voltage and low voltage power supply, lighting and power, grounding and SPDA, SDAI, CCTV, hydraulic installations - cold water, sewage and storm water, drainage and hydrant network.
São Paulo/SP
5 months
8.609,2 m²
Engenharia
Operação e Manutenção